PPAP and first article inspection (FAI) are both approvals a supplier needs before shipping production parts, and customers sometimes ask for both. They answer different questions. FAI asks whether the first part made by the production process meets every requirement on the drawing. PPAP asks whether the process itself is understood and capable of making conforming parts consistently, at the quoted rate.

Side by side

First article inspectionPPAP
ProvesThe part meets the designThe process makes conforming parts consistently
Main industryAerospace and defenseAutomotive; aerospace through AS9145
StandardAS9102AIAG PPAP manual; AS9145
SampleOne part from the first production runParts from a significant production run
EvidenceForms 1, 2 and 3: part, materials and processes, every characteristicUp to 18 elements: PFMEA, control plan, MSA, capability, dimensional and material results, warrant
StatisticsNot requiredMeasurement system analysis and initial process capability
Redo whenA change affects fit, form or function, or after a two-year lapseDesign, process, tooling, source or location changes, or 12 months inactive
ApprovalFAIR reviewed and acceptedWarrant approved, interim approved or rejected

What they share

Both start from a ballooned drawing with every characteristic numbered, and both need actual measured values, calibrated gages and material and process certificates. The PPAP dimensional results element is close to an FAI Form 3; the difference is what surrounds it. See AS9102 Form 3, field by field and PPAP levels and the 18 elements.

When you need both

AS9145, the aerospace standard for advanced product quality planning and PPAP, includes the first article inspection report as one of its PPAP elements. So an aerospace customer who flows down AS9145 gets the FAI inside the PPAP. A supplier serving both automotive and aerospace customers may run an AIAG PPAP for one and an FAI for the other on similar parts. See AS9145 for small suppliers.

Which does your customer want?

Read the purchase order and the supplier quality requirements: they name the standard, the level or form revision, and what must be submitted before the first shipment. If they name neither and you supply aerospace, an AS9102 FAI is the usual expectation; if automotive, a level 3 PPAP.

Quality Plans in FactoryQA: the APQP chain from ballooned drawing to PPAP.

In FactoryQA both come from the same ballooned drawing. Characteristics flagged for AS9102 build Forms 1, 2 and 3, and a PPAP lists the 18 AIAG elements for the level you pick, with the ballooning, process flow, PFMEA and control plan linked as evidence. See Quality Plans and Inspection.

Frequently asked questions

What is the difference between PPAP and FAI?

FAI verifies that one part from the first production run meets every drawing requirement. PPAP shows the production process is understood and capable, with evidence such as a PFMEA, control plan, measurement system analysis and capability studies.

Is FAI part of PPAP?

In aerospace, yes: AS9145 lists the first article inspection report as a PPAP element. In the automotive AIAG PPAP, the dimensional results element plays a similar role but is not an AS9102 FAI.

Does aerospace use PPAP?

Increasingly. AS9145 defines APQP and PPAP for aviation, space and defense, and several primes flow it down to suppliers alongside AS9102.

Do I need both a PPAP and an FAI?

Only if your customer requires both. Check the purchase order and supplier quality requirements, which name the standard and what to submit before first shipment.

Which comes first, FAI or PPAP?

The FAI is performed on a part from the first production run, and its report then becomes evidence within the PPAP package when both are required.

Try it on your own process: start free.