AS9145 brings two automotive ideas, advanced product quality planning (APQP) and the production part approval process (PPAP), into aerospace and defense. More primes now flow it down, and a small build-to-print machine shop can find it on a purchase order with little explanation. The good news: most of it applies to whoever owns the design, and the part that applies to you is work a good shop already does.
| Phase | What happens | Build-to-print supplier |
|---|---|---|
| 1. Planning | Requirements, risks and the project plan | Contract review: understand every requirement flowed down |
| 2. Product design and development | The design and its DFMEA | Usually not applicable: the customer owns the design |
| 3. Process design and development | Process flow, PFMEA, control plan, work instructions | Your main work |
| 4. Product and process validation | Production run, FAI, measurement and capability studies, PPAP approval | Your main work |
| 5. Ongoing production | Monitoring, corrective action and improvement | Keep the control plan and PFMEA current |
AS9145 lists eleven PPAP elements, fewer than the 18 in the automotive manual:
Your customer decides which elements are submitted, which are kept on file, and which form they want for the approval.
Capability studies assume enough parts to measure. A job shop making twelve pieces cannot produce a meaningful Cpk. Say so early: agree with the customer on an alternative such as 100% inspection of key characteristics, or data gathered across a part family or repeated lots. Do not submit a statistic from five parts and hope.
Related: PPAP vs FAI, PPAP levels and the 18 elements and AI for PFMEAs and control plans.
In FactoryQA, Set up APQP on a ballooned drawing creates the part's process flow chart, PFMEA, control plan, inspection sheets and PPAP from the drawing, linked to each other, and the AI assistants draft in line with AS9100 and AS9145 for an aerospace company. See Quality Plans.
The aerospace standard that defines advanced product quality planning (APQP) and the production part approval process (PPAP) for aviation, space and defense, organized in five phases from planning to ongoing production.
Yes, when a customer flows it down, but the design phase usually does not apply. A build-to-print supplier concentrates on process design, validation and ongoing production.
Eleven, including the process flow diagram, PFMEA, control plan, measurement system analysis, initial capability studies and the AS9102 first article inspection report.
No. AS9100 requires planning and control of production; AS9145 becomes a requirement only when a customer flows it down in a contract or supplier requirements.
Agree an approach with your customer before production: for example 100% inspection of key characteristics, or data across a part family or repeated lots, in place of a capability index from too few parts.