Written by FactoryQA quality team | Nov 29, 2026, 4:28:00 PM

AS9145 brings two automotive ideas, advanced product quality planning (APQP) and the production part approval process (PPAP), into aerospace and defense. More primes now flow it down, and a small build-to-print machine shop can find it on a purchase order with little explanation. The good news: most of it applies to whoever owns the design, and the part that applies to you is work a good shop already does.

The five phases

PhaseWhat happensBuild-to-print supplier
1. PlanningRequirements, risks and the project planContract review: understand every requirement flowed down
2. Product design and developmentThe design and its DFMEAUsually not applicable: the customer owns the design
3. Process design and developmentProcess flow, PFMEA, control plan, work instructionsYour main work
4. Product and process validationProduction run, FAI, measurement and capability studies, PPAP approvalYour main work
5. Ongoing productionMonitoring, corrective action and improvementKeep the control plan and PFMEA current

The PPAP elements in AS9145

AS9145 lists eleven PPAP elements, fewer than the 18 in the automotive manual:

  1. Design records
  2. Design FMEA, when you are responsible for the design
  3. Process flow diagram
  4. Process FMEA
  5. Control plan
  6. Measurement system analysis
  7. Initial process capability studies
  8. Packaging, preservation and labeling approvals
  9. First article inspection report (AS9102)
  10. Customer PPAP requirements
  11. PPAP approval form

Your customer decides which elements are submitted, which are kept on file, and which form they want for the approval.

A minimum that satisfies most customers

  • A process flow for the part, from receiving to shipping, including outside processes
  • A PFMEA covering each step, with the customer's key characteristics identified
  • A control plan that matches the flow and the PFMEA, line for line
  • An AS9102 first article report on a production part
  • Gage R&R on the gages that measure key characteristics (see how to calculate gage R&R)
  • Capability data on key characteristics, when quantities allow
  • The signed approval form

The low-volume problem

Capability studies assume enough parts to measure. A job shop making twelve pieces cannot produce a meaningful Cpk. Say so early: agree with the customer on an alternative such as 100% inspection of key characteristics, or data gathered across a part family or repeated lots. Do not submit a statistic from five parts and hope.

Common findings

  • The process flow, PFMEA and control plan do not match each other
  • Key characteristics on the drawing are missing from the control plan
  • Outside special processes are left out of the flow
  • No measurement system analysis for the gages used on key characteristics
  • The package is built once for approval and never updated after a change

Related: PPAP vs FAI, PPAP levels and the 18 elements and AI for PFMEAs and control plans.

Quality Plans in FactoryQA: the APQP chain from ballooned drawing to PPAP.

In FactoryQA, Set up APQP on a ballooned drawing creates the part's process flow chart, PFMEA, control plan, inspection sheets and PPAP from the drawing, linked to each other, and the AI assistants draft in line with AS9100 and AS9145 for an aerospace company. See Quality Plans.

Frequently asked questions

What is AS9145?

The aerospace standard that defines advanced product quality planning (APQP) and the production part approval process (PPAP) for aviation, space and defense, organized in five phases from planning to ongoing production.

Does AS9145 apply to build-to-print suppliers?

Yes, when a customer flows it down, but the design phase usually does not apply. A build-to-print supplier concentrates on process design, validation and ongoing production.

How many PPAP elements does AS9145 have?

Eleven, including the process flow diagram, PFMEA, control plan, measurement system analysis, initial capability studies and the AS9102 first article inspection report.

Is AS9145 required for AS9100 certification?

No. AS9100 requires planning and control of production; AS9145 becomes a requirement only when a customer flows it down in a contract or supplier requirements.

How do I show capability on low-volume parts?

Agree an approach with your customer before production: for example 100% inspection of key characteristics, or data across a part family or repeated lots, in place of a capability index from too few parts.