title: How to fill out a PSW (part submission warrant) | FactoryQA
description: "How to fill out a part submission warrant (PSW) field by field: part details, submission reason and level, results, declaration, and why warrants get rejected."
---

[Quality Management Guides and Resources | FactoryQA](https://factoryqa.com/resources)

# [How to fill out a PSW (part submission warrant) | FactoryQA](https://factoryqa.com/resources/part-submission-warrant-guide)

 Written by [FactoryQA quality team](https://factoryqa.com/resources/author/factoryqa-quality-team) | Nov 29, 2026, 4:27:12 PM

The part submission warrant (PSW) is the one page that summarizes a whole PPAP. Signing it declares that your parts meet every drawing and specification requirement and were made on the production process, at the production rate. It is also the page customers reject most often for small mistakes. This guide goes through the form in the AIAG PPAP manual (4th edition) section by section.

PPAP package**The elements for the level**Dimensional, material, capability

Part and drawing identificationReason and submission levelResults and declarationSignature, then customer disposition

## Part information

| Field | What goes in it |
| --- | --- |
| Part name and customer part number | Exactly as on the drawing and the purchase order. *Watch for: your internal number in the customer's field.* |
| Shown on drawing number | The drawing that defines the part, if it differs from the part number. |
| Organization part number | Your own part number, if you use one. |
| Engineering change level and date | The drawing revision the samples were made to, and its date. *Watch for: a revision that does not match the PO.* |
| Additional engineering changes | Authorized changes not yet on the drawing. |
| Safety or government regulation | Yes or no, according to the drawing. |
| Purchase order number and weight | The PO, and the part weight in kilograms to four decimal places, measured on real parts. |
| Checking aid number, change level and date | Only if a part-specific checking fixture is used. |

## Who made it, and for whom

Enter the manufacturing site that made the samples, with its name, address and the supplier code your customer assigned, then the customer's name and division, the buyer and the application (the model or program the part goes into). The site must be where production will run: samples made at another plant do not represent the process.

## Materials reporting

State whether substances of concern have been reported as the customer requires (in automotive, usually through IMDS), and whether polymeric parts carry the required ISO marking codes. If neither applies, say so instead of leaving the boxes empty.

## Reason for submission

Tick the one reason that applies: initial submission, engineering change, tooling transfer, replacement or refurbishment, correction of a discrepancy, tooling inactive for more than a year, a change to construction or material, a change of sub-supplier or material source, a change in part processing, parts produced at an additional location, or other with an explanation. The reason tells the customer what changed, so it should match what you told them when the change was approved.

## Requested submission level

Tick the level your customer asked for. Level 3 is the default when none is specified. See [PPAP levels and the 18 elements](https://factoryqa.com/resources/ppap-levels-and-elements) for what each level sends.

## Submission results

Tick the results the submission includes (dimensional measurements, material and functional tests, appearance criteria, statistical process package) and state whether they meet all design record requirements. If the answer is no, explain: an honest no with a plan is better than a yes the customer disproves. Enter the mold, cavity or production process the samples came from when there is more than one.

## Declaration

The declaration says the samples are representative of your parts, were made by the production process, and meet the requirements. Fill in the production rate the run achieved, as parts per number of hours, and note any deviations in the comments. Confirm customer-owned tooling is tagged and numbered, then sign with your printed name, title, phone, email and the date. The signer must be authorized by your organization, and should sign only when the evidence is complete.

## For customer use

Leave the disposition box for your customer: approved, rejected or other, with their signature and date. Keep the signed copy with the PPAP record for as long as the part is active plus the retention period your customer requires.

## Why PSWs get rejected

- The drawing revision or part number does not match the purchase order
- Weight missing, estimated, or not in kilograms to four decimal places
- More than one reason for submission ticked, or none
- Results marked as meeting requirements when the dimensional report shows an out-of-tolerance value
- Production rate left blank
- Signed before the capability or measurement studies were finished
- One warrant covering several part numbers without the customer's agreement

Quality Plans in FactoryQA: the APQP chain from ballooned drawing to PPAP.

In FactoryQA, a PPAP holds the part details, the 18 elements and their evidence. Click Generate PSW and the warrant is created as a Word document from the package details and added to the package documents, ready to check and sign. An AI review of the package scores its readiness and lists findings for each element before you submit. See [Quality Plans](https://factoryqa.com/products/quality-plans).

## Frequently asked questions

### What is a part submission warrant?

The PSW is the summary form of a PPAP. It identifies the part and revision, the reason and level of the submission and the results, and carries a signed declaration that the parts meet every requirement.

### Who signs the PSW?

An authorized representative of the supplier, usually the quality manager or another responsible official. The customer then records the disposition: approved, rejected or other.

### Is a PSW required at every PPAP level?

Yes. The warrant is submitted at levels 1 to 4 and retained for review at level 5. It is the one element every submission includes.

### How is the part weight on a PSW determined?

By weighing sample parts and reporting the average in kilograms to four decimal places, without packaging or shipping protection, unless the customer specifies otherwise.

### Do I need a separate PSW for each part number?

Normally yes: one warrant for each customer part number, unless the customer agrees to cover a family of parts on one.

[View full post](https://factoryqa.com/resources/part-submission-warrant-guide)

```json
{
  "@context" : "http://schema.org",
  "@type" : "BlogPosting",
  "author" : {
    "@type" : "Person",
    "name" : "FactoryQA quality team"
  },
  "dateModified" : "2026-11-29T16:27:12.870Z",
  "datePublished" : "2026-11-29T16:27:12Z",
  "headline" : "How to fill out a PSW (part submission warrant)",
  "image" : {
    "@type" : "ImageObject",
    "height" : 630,
    "url" : "https://factoryqa.com/hubfs/fqa-og-res-part-submission-warrant-guide.png",
    "width" : 1200
  },
  "mainEntityOfPage" : "https://factoryqa.com/resources/part-submission-warrant-guide",
  "publisher" : {
    "@type" : "Organization",
    "logo" : {
      "@type" : "ImageObject",
      "height" : 60,
      "url" : "/hs/hsstatic/content_shared_assets/static-1.4092/img/default-amp-logo.png",
      "width" : 60
    },
    "name" : "FactoryQA Resources"
  }
}
```